Construction Progress


Five dormitories are currently under construction.
Dormitory A1 will accommodate 120 people, include 2 meeting rooms and have 22 bathrooms. It is currently 11% complete and scheduled for completion in February 2011.



Dormitory A2 will accommodate 120 people, include 2 meeting rooms and have 22 bathrooms. It is currently 11% complete and scheduled for completion in February 2011.






Dormitory A3 will accommodate 120 people, include 2 meeting rooms and have 22 bathrooms. It is currently 71% complete and scheduled for completion in February 2011.



Dormitory B1 will accommodate 80 people, include 2 meeting rooms and have 22 bathrooms. It is currently 7% complete and scheduled for completion in February 2011.





Dormitory B2 will accommodate 80 people, include 2 meeting rooms and have 22 bathrooms. It is currently 11% complete and scheduled for completion in February 2011.


The Multipurpose Building will comprise of an Assembly Hall seating between 600-800 people, training, conference and worship rooms and a kitchen and dining hall with seating inside and out.


It is currently 18% complete and scheduled for completion in February 2011.